Sunnybrook Hospital M Wing Expansion
In simple terms, Vanbots added four levels to the M-Wing at Sunnybrook Health Sciences Centre. In no way was the project simple in the intricacies of its execution. They threaded structural steel though the very heart of the hospital, working directly over the Operating Theatres, and managing the schedule to ensure compliance with the Build Finance targets.
What made this project so special and challenging was controlling the indoor environment of the existing hospital. They mostly worked at night and had to take incredible measures to control humidity, noise, dust and vibration. They had to be prepared to cancel work without notice the moment they heard an incoming medi-vac helicopter approaching the campus.